Mina Justa

Project Stages

The development stages in the projects are displayed in the standard sequence for the industry. However, projects may be developed in a different sequence because of corporate decisions or events that push the owner to repeat stages. To access the full details of this project’s history please explore its milestones

Early Works
Current Stage: Feasibility
Start: 08/2016
Completion: 12/2018
In Construction
Under Construction
Start: 12/2018
Completion: 03/2021
Ramp up / Commissioning
Completion: 03/2021
Project Details


The Mina Justa open pit copper oxide mine is targeted to have copper oxides and sulfides resources reaching 374Mt at an average grade of 0.71%. The project will require 1,400 workers during the construction phase and will then generate 300 jobs during the ensuing operational phase.

Only BNamericas Subscribers Can Access This Information.
Subscribe to BNamericas to gain better insight into project development and contract opportunities in Latin America.
  • Early-stage and under-development projects throughout the region
  • Project coverage focused on biggest investments in each country and sector
  • Project milestones highlighting planned and unplanned developments
  • Sales contacts within operators and contracted companies
  • Access to experienced research staff
  • Risk analysis of cost increases, scheduling conflicts and regulatory environment
Already a subscriber? Please, login

Milestones Log and News

Principal Works

Locked content
Dear visitor, this table includes insights that is only available for subscribers

Related Companies

Name Sector Country Relation
Locked content
Project Owners
Locked content
Former Owner
Locked content
Locked content
Locked content
Locked content
Locked content
Locked content
Dear visitor, this table includes insights that is only available for subscribers

  • * Figures and dates are as per the latest publicly available information, as well as information gathered by BNamericas reporters and analysts and are subject to change.

  • * Changes to original budget estimates are shown as the total figure available and may include interest, working capital, inflation adjustments and other contingencies in addition to capital expenditure.

  • * Amounts and overall results are shown in US dollars unless otherwise stated.

  • * BNamericas does not guarantee the sequence, accuracy, adequacy, completeness or availability of any information and is not responsible for any errors or omissions or for the results obtained from the use of such information. There are no express or implied warranties. In no event shall BNamericas, its agents, directors, officers, employees, representatives, successors, and assigns be liable for any damages of any nature in connection with BNamericas content.

Key Specs

Full Name
Mina Justa
Project Type
Copper, Open pit mining, Underground mining
Development Phase
Project Status
Project Capacity
110,000  t/y (tons per year)  Copper
 Open pit mining
 Underground mining
US$ 1.5bn
Completion Date

Mine Justa lies 30km from the Pacific Ocean in Nazca province in Peru's Ica department. The elevations of the property range from about 800m to 1,800m above sea level.

* The map coordinates represent the approximate latitude and longitude, and not the exact location of the project.

Locked content
Owner / operator
Locked content
Project Manager
Locked content
Exploration Manager
Locked content
Supply and Contracts Manager
Locked content
Engineering and Project Development Manager
Locked content
Administration and Finance Manager
Locked content
Procurement Manager
Locked content
Operations Manager
Locked content
Senior Geologist
Dear visitor, this table includes insights that is only available for subscribers